What is a superload?

There is no federal answer. Each state sets its own trigger, and they are not close to each other — 16 feet wide in 20 states, but the range runs from 14 to 18.

8 min read·Last updated 28 July 2026· Checked against 48 state DOT sources
Jump to a section
  1. What a superload actually is
  2. Where each state draws the line
  3. Superload triggers, all 48 states
  4. How long review takes
  5. What the review involves
  6. Planning a superload move
  7. Common questions

What a superload actually is

A superload is not a bigger oversize permit. It is a different process. Below a state’s superload line, a permit is an administrative act — you apply, the system checks your numbers against a table, and a permit comes back. Above that line, the state stops treating your load as paperwork and starts treating it as an engineering problem: which bridges will carry it, which overpasses it fits under, which turns it can physically make.

That is why the word matters even though no two states define it the same way. Crossing the line changes the lead time, the documentation, and often the escorts — not just the fee.

The trap on multi-state routes

You can be a routine oversize load in one state and a superload in the next one on the same trip. A 16-foot-wide load is under the line in the 20 states that trigger at 16 feet, and over it in the seven that trigger lower. Plan to the strictest state on the route, not the one you load in.

Where each state draws the line

Four dimensions can push a load into superload review, and states do not agree on any of them. Width is the most commonly published trigger; weight is the most commonly published overall.

Width triggers across the 48 contiguous states
Superload atStatesNotes
14′0″2The strictest line in the country — barely over a legal-width-and-a-half load.
14′6″1
15′0″5
16′0″20The most common figure, and the one worth memorising.
16′6″2
17′0″4
18′0″2The most permissive published line.
Not published12No table figure. Decided when you apply, on the route you give them.

Of the four dimensions, weight is published by the most states — 39 of 48 — and it is where the spread is widest. Some states start superload review at 120,000 lb gross; others not until 500,000 lb. Height triggers are published by 31 states and cluster at 16 feet. Length is published by 29.

Width trigger
36 of 48
Weight trigger
39 of 48
Height trigger
31 of 48
Length trigger
29 of 48

Superload triggers, all 48 states

Exceed any one of these and the load goes to review in that state. Where a cell says Not published, the state has no figure in its published tables — it is decided on application. That is not the same as no limit.

Superload triggers and published review windows, 48 contiguous states
StateWidthHeightLengthGross weightReview
Alabama16'16'150'300,000 lb3 days
Arkansas16'6"15'6"100'180,000 lbNot published
Arizona16'16'120'250,000 lb14 days
California15'17'135'Not published30 days
ColoradoNot publishedNot publishedNot published500,000 lb5 days
Connecticut16'16'150'200,001 lb5 days
Delaware15'15'120'120,000 lb14 days
Florida16'18'150'200,000 lb10 days
Georgia16'16'Not published180,001 lbNot published
IowaNot publishedNot publishedNot publishedNot publishedNot published
Idaho16'16'120'Not publishedNot published
Illinois14'6"15'145'120,000 lbNot published
Indiana16'15'110'120,000 lbNot published
Kansas16'6"18'126'150,000 lbNot published
Kentucky16'Not published120'160,000 lbNot published
LouisianaNot publishedNot publishedNot published232,000 lb28 days
MassachusettsNot publishedNot publishedNot published130,000 lb10 days
Maryland16'16'100'150,000 lb2 days
Maine16'15'125'160,000 lbNot published
Michigan16'15'150'Not published10 days
Minnesota16'16'150'250,000 lbNot published
Missouri16'16'150'160,000 lb14 days
Mississippi17'15'7"121'189,999 lbNot published
Montana18'17'150'Not published2 days
North Carolina17'Not publishedNot published132,000 lb14 days
North DakotaNot publishedNot publishedNot published200,000 lbNot published
Nebraska16'15'11"150'160,000 lb10 days
New Hampshire15'13'6"110'150,000 lb30 days
New JerseyNot publishedNot publishedNot publishedNot publishedNot published
New MexicoNot publishedNot publishedNot published170,000 lbNot published
Nevada17'18'200'500,000 lb10 days
New York16'16'160'200,000 lb10 days
Ohio14'14'6"Not published120,000 lbNot published
OklahomaNot publishedNot publishedNot published209,000 lbNot published
Oregon14'17'150'900,000 lb10 days
Pennsylvania16'Not published160'201,000 lbNot published
Rhode IslandNot publishedNot publishedNot published200,000 lbNot published
South CarolinaNot publishedNot publishedNot published130,000 lbNot published
South DakotaNot publishedNot publishedNot publishedNot publishedNot published
Tennessee16'15'6"Not publishedNot publishedNot published
TexasNot publishedNot publishedNot published254,301 lb42 days
Utah17'17'6"Not publishedNot published14 days
Virginia15'15'150'115,000 lb10 days
Vermont15'14'100'150,000 lb10 days
Washington16'16'125'200,000 lb30 days
Wisconsin16'Not publishedNot published150,001 lbNot published
West Virginia16'Not publishedNot published120,001 lb2 days
Wyoming18'17'120'160,001 lb3 days

How long review takes

Twenty-six states publish a review window. The other 22 do not, which is itself useful information: those are the states where you should apply earlier than feels necessary, because the answer depends on what the bridge engineers find.

Published superload review windows
Review windowStatesWhat it means for planning
5 days or less7Same working week, if nothing on the route needs a survey.
10 days9The most common figure. Two working weeks is the safe assumption.
14 days5Plan the load before you book the freight.
28 days or more5Up to 42 days in the slowest state. These need to be in motion a month out.
Not published22No committed window. Treat as two weeks minimum and ask early.

The published window is the review, not the trip. It starts when the state has a complete application — dimensions, axle spacings, weights per axle, and the exact route. An incomplete application does not start the clock, which is the single most common reason a superload runs late.

What the review involves

The specifics vary, but a superload review is usually some combination of four things:

  • Bridge and structure analysis. The state models your axle weights and spacings against every structure on the route. This is why axle spacing matters as much as gross weight — the same 200,000 lb spread over more axles may pass where a tighter configuration fails.
  • Route survey. A physical drive of the route confirming vertical and horizontal clearance. Several states trigger this on dimension alone, not on superload status.
  • Escort and police requirements. Superloads commonly pick up requirements beyond the ordinary escort table — additional vehicles, police at specific points, or utility crews for overhead lines.
  • Movement restrictions. Tighter windows than a routine oversize permit: off-peak only, weekdays only, or specified hours through metropolitan areas.

Planning a superload move

Three things save the most time, in order:

  • Fix the route before you apply. Review is route-specific. Changing the route after submission generally restarts it.
  • Have the axle detail ready. Axle count, individual axle weights and spacings, and the tractor configuration. Gross weight alone is not enough for a structure analysis.
  • Apply to the slowest state first. On a multi-state route the critical path is whichever state has the longest review, not the first one you enter.

Common questions

What is a superload?

A superload is a load so far over legal size or weight that the state will not issue it as a routine oversize permit. Instead it goes to engineering review. There is no federal definition — each state sets its own trigger, and the numbers are not close to each other. Sixteen feet wide is the most common width trigger, used by 20 states, but the range across the country runs from 14 feet to 18 feet.

At what width does a load become a superload?

Twenty states set the line at 16 feet wide. Five use 15 feet, four use 17 feet, two use 18 feet, two use 14 feet, and single states use 14′6″ and 16′6″. Twelve states publish no width trigger at all, which does not mean there is no threshold — it means it is decided case by case when you apply.

How long does a superload permit take?

Of the 26 states that publish a review window, the shortest is two days and the longest is 42. Ten days is the most common figure. Twenty-two states publish no lead time, so the honest answer for those is that it depends on the route and the bridges on it.

Is a superload permit more expensive?

The permit fee itself is often the same as any oversize permit in that state. The cost comes from what the review requires: route surveys, bridge analysis, escorts, police, and sometimes utility crews to lift lines. Permigo charges the same $20 per state permit either way.

Do I need a route survey for a superload?

Frequently, yes — and in several states it is triggered by dimension rather than by superload status. Texas requires a route survey over 20 feet wide on divided highways, for example. The survey confirms that every overpass, bridge and turn on the route will physically take the load.

Can I run a superload at night?

Usually the opposite. Most states restrict oversize movement to daylight hours, and superloads are commonly held to even tighter windows — off-peak only, weekdays only, or with police escort at specific hours. Check the movement window on your state page.

Keep reading
Cost

Oversize permit cost by state, 2026

What each state DOT actually charges for a single-trip OS/OW permit — all 48, and why thirteen of them cannot be reduced to one number. Searchable, sortable, every figure dated and linked to its source.

8 min read · 48 states
Rules

When do you actually need an oversize permit?

The federal baseline is 8'6" wide, 13'6" high, 53' trailer and 80,000 lbs — but that height figure is only right in about half the country. Where states go stricter, and the divisible-load rule that gets drivers ticketed.

6 min read
Escorts

Pilot car requirements by state

Escort rules are a function of dimension and road tier — the same load can need a front escort on a two-lane and a rear escort on a multilane. Plus night, weekend and holiday blackouts.

7 min read

Superload on the board? Start it early.

$20 flat per state permit. We file with every DOT on the route at once and chase the reviews.